Construction Stormwater Inspection Report

Georgia NPDES General Permit GAR100001 (stand-alone construction) · Part IV.D.4 inspection
Report # SAMPLE-0928-01
Prepared with the Georgia Stormwater Log (prototype)
Project / facilityMagnolia Ridge, Lot 14 (fictional)
Site locationSample Lane, Canton, GA · Cherokee County (fictional address)
Primary permitteePinecrest Sample Homes LLC (fictional)
NOI / permitGAR100001 · GEOS submittal # 0000000 (sample)
Disturbed acreage0.62 ac (sampling not required: under 5 ac)
Receiving waterSample Creek (fictional)
Construction phase IV.D.4.a.(6)Intermediate (☐ Initial ☒ Intermediate ☐ Final)
Weather at inspectionClear, 64°F, soils damp

1. Inspection details Part IV.D.4.a.(3) and (6)

Inspection typePost-rain inspection (storm of 0.5 in or more). Per the permit, this inspection also resets the 7-day inspection frequency.
Qualifying stormEnded Fri 9/25/2026, 6:15 PM · 0.60 in recorded at the on-site rain gauge
Deadline appliedThe storm ended after 5:00 PM on a Friday and the site does not work weekends, so the inspection was due by the end of the next business day and/or working day, whichever occurs first: Mon 9/28/2026.
Date and time of inspection IV.D.4.a.(6)Mon 9/28/2026, 8:10–8:55 AM ✓ within deadline
Certified personnel making the inspection IV.D.4.a.(6)Jordan Avery (fictional) · GSWCC Level IA
Card # 00000-SAMPLE, exp. 12/2027 (optional field, recommended good practice; the permit requires the name)
Next 7-day inspection dueMon 10/5/2026 (7 calendar days from this post-rain inspection)

2. Rainfall record, last 7 days Part IV.D.4.a.(2)

DateDayWorking day?Gauge reading (in, 24 hr)Read byNote
9/22/2026TueYes0.00J. Avery
9/23/2026WedYes0.05J. Avery
9/24/2026ThuYes0.00J. Avery
9/25/2026FriYes0.10J. AveryReading at 7:30 AM. Storm began ~2:00 PM.
9/26/2026SatNo——Non-working Saturday: measurement not required
9/27/2026SunNo——Non-working Sunday: measurement not required
9/28/2026MonYes0.60 (since Fri reading)J. AveryStorm ended Fri 6:15 PM (time per crew/forecast record). ≥ 0.5 in: post-rain inspection triggered.

The permit requires rainfall to be measured and recorded within disturbed, not-yet-stabilized areas every 24 hours, except any non-working Saturday, non-working Sunday and non-working federal holiday.

3. Areas inspected Part IV.D.4.a.(1) and (3)

AreaInspectedResult
(a) Disturbed areas of the siteYesSee BMP findings
(b) Material storage areas exposed to precipitationYesNo issues: lumber covered, no bagged materials exposed
(c) Structural control measuresYesSee BMP findings
Accessible discharge locations/points (effectiveness in preventing significant impacts to receiving waters)YesDischarge at rear swale clear. No sediment observed leaving site.
Petroleum storage/handling areas: spills or leaks (daily item)YesNo leaks observed at fuel can storage
Construction exit: off-site sediment tracking (daily item)YesTracking observed onto street (see #3 below)

4. Major observations and BMP findings Part IV.D.4.a.(6)

#BMP / location (per ES&PC Plan)StatusObservation
1Sd1 silt fence (Type S), rear lot lineNot maintained~10 ft section undermined at low point. Sediment at about 1/2 the fence height upslope.
2Inlet protection (Sd2), curb inlet at lot frontageNot maintainedSediment accumulation reduces capacity. Needs cleanout.
3Construction exit (Co), drivewayNot maintainedStone voids filled with mud. Tracking onto Sample Lane.
4Temporary seeding/mulch (Ds2), side slopesOKCoverage ~70%, establishing. No rills.
5Concrete washout, NE cornerOKLined, under 50% full.

Incidents of BMPs not properly installed and/or maintained as described in the Plan: #1, #2, #3 (identified as required by Part IV.D.4.a.(6)). Because incidents were found, the "no incidents" compliance certification below does not apply to this report.

5. Actions taken / required Part IV.D.4.a.(5)

#Corrective actionPlan revision needed?Due (≤ 7 calendar days)Completed
1Re-trench and re-stake undermined silt fence section. Remove accumulated sediment.No10/5/20269/29/2026 · J. Avery
2Clean out inlet protection. Replace filter fabric.No10/5/20269/28/2026 · J. Avery
3Top-dress construction exit with stone; sweep street.No10/5/20269/28/2026 · J. Avery

Per Part IV.D.4.a.(5), the Plan shall be revised as appropriate within 7 calendar days of the inspection, and changes implemented as soon as practical but within 7 calendar days.

6. Certification and signature Part V.G.2

"I certify under penalty of law that this report and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that certified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations."

When no incidents are found, the report must instead contain a certification that the BMPs are in compliance with the Erosion, Sedimentation and Pollution Control Plan (Part IV.D.4.a.(6)). The log adds this automatically when every BMP is marked OK.

Sam Pinecrest
Signature: permittee or duly authorized representative (Part V.G.2)
Sam Pinecrest, Owner
Printed name and title (fictional)
9/28/2026
Date